NEWS
Stranded Equipment, Starved Power Plants Compound Nigeria’s Electricity Crisis
Stranded Equipment, Starved Power Plants Compound Nigeria’s Electricity Crisis
Gas shortages, lower hydroelectric output and maintenance problems have reduced electricity supply across Lagos, Ogun, Oyo, Kwara and Abuja.
Nigeria’s power plants used 518 million standard cubic feet of gas daily in September, 4% less than in August.
The national grid allocated 2,926 megawatts to 11 distribution companies on November 5.
Government officials have cleared 44 of more than 300 containers of stranded power equipment, some held at Apapa Port since 2014.

November 06, () – Electricity shortages have returned to parts of Lagos, Abuja, Ogun, Oyo and Kwara, leaving households and businesses with fewer hours of power as Nigeria’s generating stations contend with inadequate gas supplies and declining hydroelectric output.
The Minister of Power, Joseph Tegbe, acknowledged the disruptions on Thursday, November 5, after complaints from electricity consumers who had recently experienced improvements in supply.
He attributed the deterioration to reduced gas availability, maintenance problems and lower water inflows into hydroelectric reservoirs. Preliminary assessments, he said, found no major failure of the national grid.
Every second brings Nigerians closer to exercising their democratic right and shaping the future of our nation.
Exercise your democratic right responsibly, peacefully and lawfully.
The Nigerian Independent System Operator (NISO) separately confirmed that the constraints had reduced generation and forced distribution companies to ration available electricity.
At 4.41 p.m. on Thursday, the grid allocated a combined 2,926 megawatts to Nigeria’s 11 electricity distribution companies. Abuja Electricity Distribution Company received 633MW, followed by Ibadan DisCo with 391MW and Port Harcourt DisCo with 320MW.
Channel
The figures represent electricity allocated at a particular time, not the amount consumers ultimately received. Network faults, distribution capacity and local load-shedding arrangements can further affect supply.
Gas Shortages Leave Less Electricity To Distribute
A trader refuels a petrol generator at a Lagos market Source Bloomberg
Nigeria depends heavily on gas-fired power stations and hydroelectric plants to supply its national grid. Problems affecting both sources therefore reduce the amount of electricity available before distribution companies can deliver power to consumers.
Figures from the Nigerian Midstream and Downstream Petroleum Regulatory Authority show that power plants consumed an average of 518 million standard cubic feet of gas daily in September 2026, down 4% from August.
The regulator’s figures establish an earlier decline in gas use by power plants, although they do not independently quantify the supply shortfall responsible for this week’s outages.
NISO also reported lower water inflows into hydroelectric reservoirs, which have limited the output of affected generating stations.
Its generation dashboard recorded 2,556.06MW from 15 reporting power plants at 3 p.m. on November 5. Several stations reported no output at that time.
Generation and distribution-allocation figures taken at different hours should not be compared as though they describe the same operating conditions. Both sets of data, however, show the pressure on available electricity.
The effect reaches beyond household inconvenience. Manufacturers need dependable power to operate machinery, preserve materials and complete production schedules, while traders and service businesses must pay for alternative electricity when grid supply falls.
Manufacturers Association of Nigeria figures put industrial spending on alternative power at approximately ₦1.35 trillion in 2025, compared with about ₦1.11 trillion in 2024.
Those figures predate the latest disruptions and do not measure their immediate financial impact. They nevertheless establish how expensive unreliable electricity had already become for manufacturers.
A business that switches to diesel- or gas-powered generators or battery storage must pay to keep equipment running even when production or sales remain unchanged. Frequent interruptions can also damage machinery, delay deliveries and reduce working hours.
Tegbe has directed the Transmission Company of Nigeria, NISO and distribution companies to address operational problems and accelerate maintenance. The ministry has not announced a definite date for restoring normal supply.
Over 250 Containers Still Await Clearance At Apapa
The latest outages coincide with a separate effort to recover electricity equipment that Nigeria procured but failed to deploy.
Following President Bola Tinubu’s intervention, the Federal Ministry of Power worked with the Nigeria Customs Service and Nigerian Ports Authority to clear 44 containers from Apapa Port.
Officials said more than 300 containers had remained stranded before the intervention, with some held since 2014.
The President directed the relevant agencies to reconcile outstanding charges and remove the administrative obstacles preventing their release.
Tegbe said engineers would inspect the recovered equipment to establish what remained serviceable. Government agencies would then deploy usable components to electricity projects and dispose of items that could no longer serve their intended purpose.
The ministry has not published a complete inventory of the 44 containers, their original procurement costs, the projects awaiting them or a schedule for installation.
Earlier recovery work by the Niger Delta Power Holding Company retrieved 110 containers and 216 packages of abandoned equipment. The company reported savings exceeding ₦30 billion and said recovered turbines helped unlock approximately 470MW of generation capacity.
Those claims concern an earlier exercise, not the 44 containers released this week.
Recovering equipment can help address infrastructure problems, but transformers, turbines and other components cannot substitute for the gas needed to operate thermal stations. Their usefulness also depends on their condition, installation requirements and the readiness of the projects receiving them.
Nigeria’s latest electricity shortages therefore demand more than repairs to individual power lines or the release of stranded equipment.
Authorities must restore adequate fuel supply to generating plants, resolve operating problems and establish how quickly recovered infrastructure can contribute to the grid.
Publishing plant-level generation losses, restoration schedules and the status of the remaining containers would also allow electricity consumers to assess progress against the government’s assurances.
Until supply improves, businesses and households will continue paying for electricity twice in different ways, through the grid when it is available and through alternative systems when it is not.