After 20 Years, Customs Frees 98 Containers Of Electricity Equipment

Published

on

After 20 Years, Customs Frees 98 Containers Of Electricity Equipment

After 20 Years, Customs Frees 98 Containers Of Electricity Equipment

The Nigeria Customs Service (NCS) has released 98 containers of electricity transmission equipment that had been stranded at the nation’s ports, some for as long as 20 years, in a move aimed at strengthening the national grid and improving electricity supply.

The Minister of Power, Joseph Tegbe, disclosed this in Lagos, explaining that 44 containers were cleared from ENL Terminal, while another 54 were released from APMT and Sun & Moon Terminals.

According to the minister, the 98 containers constitute part of more than 300 containers of transmission equipment that had remained trapped at the ports for several years.

The recovered equipment includes high-capacity transformers, cables and switchgear procured to expand the country’s transmission network, ease pressure on overloaded substations and improve electricity distribution nationwide.

Tegbe explained that the prolonged detention of the equipment had stalled critical power projects, left existing substations under considerable strain and exposed valuable assets to deterioration, while also attracting additional port charges.

He said, “The equipment was procured to expand the transmission network and relieve overloaded substations. Its detention stalled projects, kept existing substations under heavy strain, exposed valuable assets to deterioration and accumulated charges on the cargoes.”

The minister added that the delay had further increased costs for businesses, households and public institutions, which continue to contend with unreliable electricity supply.

Also speaking, the Comptroller-General of Customs, Bashir Adeniyi, said the Service had begun working with the Ministry of Power, the Nigerian Ports Authority and terminal operators to facilitate the clearance of the remaining containers.

FEDERAL REPUBLIC OF NIGERIA GENERAL ELECTION COUNTDOWN
◷ 00:00:00 WAT
✓ YOUR VOTE • YOUR VOICE • YOUR FUTURE
NIGERIA GENERAL ELECTION

Every second brings Nigerians closer to exercising their democratic right and shaping the future of our nation.

📅 16 January 2027
📍 Nigeria
⏰ 12:00 AM WAT
📆
000
DAYS
🕐
00
HOURS
⌛
00
MINUTES
⏱
00
SECONDS
🇳🇬 COUNTDOWN PROGRESS 0%
🪪 Voter Information
✅ Vote Peacefully
🇳🇬 Nigeria Decides
✓
ELECTION DAY IS HERE!

Exercise your democratic right responsibly, peacefully and lawfully.

He attributed the latest release to President Bola Tinubu’s directive for the immediate evacuation of the equipment and the resolution of outstanding charges and administrative bottlenecks.

“The release follows the President’s directive for immediate clearance and for agencies to resolve outstanding charges and administrative bottlenecks without delay,” Adeniyi said.

Connect with Media Today
Channel
Media Today Facebook
f Join Facebook Page
Media Today WhatsApp Group
◉ Join WhatsApp Group
Media Today WhatsApp Channel
◉ Join WhatsApp Channel
Media Today Telegram
➤ Join Telegram Channel
Media Today Google News
G Follow on Google News
Media Today Google Discover
G Add Us on Google Discover
Media Today Nairaland
N Follow Us on Nairaland

The Customs boss pledged the Service’s continued collaboration with the Ministry of Power until all the stranded containers were released, while appealing to terminal operators to support the exercise in the national interest.

Advertisement

Meanwhile, Tegbe disclosed that an inspection of the recovered equipment showed that most of the items remained useful and could still be deployed after necessary assessments.

He said the equipment would undergo verification, testing and refurbishment where necessary before being moved to designated project sites.

“When evacuated, it will be verified, tested and refurbished where necessary, then deployed to project sites to complete stalled installations, relieve overloaded substations and strengthen constrained transmission corridors,” he said.

READ THIS  NLC Gives FG Two Weeks to Cut Petrol Price, Renegotiate Minimum Wage as Atiku Rejects 30-day Discount


DO YOU WANT TO WHISTLEBLOW, REPORT FRAUD, THEFT OR INJUSTICE OR INTIMIDATION? SEND US YOUR STORY/REPORT TO NEWSDESK@MEDIATODAY.NG

Continue Reading
Advertisement
Click to comment

Leave a Reply

GET SEEN. GET HEARD.

PUBLISH ANDADVERTIZE

ON MEDIA TODAY NIGERIA

News • Events • Business • Publicity

☎ CALL TO PUBLISH / ADVERTIZE +234 812 718 8384 PROMOTE • CONNECT • GROW

SPONSORED ADS

SPONSORED ADS

Recent Posts

Connect with Media Today
Channel
Media Today Facebook
f Join Facebook Page
Media Today WhatsApp Group
◉ Join WhatsApp Group
Media Today WhatsApp Channel
◉ Join WhatsApp Channel
Media Today Telegram
➤ Join Telegram Channel
Media Today Google News
G Follow on Google News
Media Today Google Discover
G Add Us on Google Discover
Media Today Nairaland
N Follow Us on Nairaland

SPONSORED

SPONSORED AD

Enable Notifications OK No thanks